Princes Drive
25,000 sqft site
Project Overview
This comprehensive demolition project involved the full-scale demo of a large mansion in Oxshott, enabling the rebuild of the site for a new residential home.
Location: Bicester
Duration: 4 Months
FULL PACKAGE COMPRISED OF:
- Carried out pre demo surveys
- Risk assessments and site setup
- Asbestos removal
- Roof Strip for ecology works
- Full demolition
- Reduced dig and piling mat
- Waste sorting and recycling
- Coordination with Local Authority
Key Achievements
- Maintained strict 3 week programme
- Liaised with local residents and ensured minimal disruption to local residents
- Implemented dust control on a live urban site
Sustainability Efforts
97%
97%
97%
Overall material recovery rate across all waste streams
0
%
of crushed 6F5 material recycled
0
%
of total waste diverted from landfill