Bicester
Project Overview
AVIDAN Group was commissioned to deliver internal demolition and asbestos removal works as part of a large-scale redevelopment of a former technical college in Bicester. The scope included pre-demolition assessments, soft strip, and the careful dismantling of key internal structures to enable full reconfiguration of the site for modern reuse.
The project also involved the sustainable processing of construction materials, with a high percentage of on-site recycling achieved — in line with environmental and client expectations.
Client: Pacey & Wheatly
Location: Bicester
Duration: 4 Months
FULL PACKAGE COMPRISED OF:
- Pre-demolition surveys and initial reporting
- Section 81 demolition notice application
- Full risk assessments
- Detailed 3D phased method statements and planning
- Internal soft strip across all levels
- Full internal demolition
- Asbestos removal and compliant waste handling
Key Achievements
- Active engagement with nearby residents to minimise disruption
- Traffic management strategy implemented to support town centre logistics
- On-time delivery against strict redevelopment deadlines
- Maintained full COVID-19 safety protocols throughout project duration
- Executed all works with zero health and safety incidents
Sustainability Efforts
94%
94%
94%
Overall material recovery rate across all waste streams
0
%
of 450 tonnes of crushed 6F5 material recycled
0
%
recovery of 37 tonnes of scrap metal