Colmore Gate
320,000 sqft site

Project Overview

This comprehensive project involved the full-strip out of a 14 floor office building located in the heart of Birmingham City Centre.

Phase 1 consisted of derating certain floors the building.

Phase 2 consisted of a soft strip of 10 floors whilst maintaining the use of floors 11-14 with live tenants.

Phase 3 consisted of a full soft strip.

Location: Centre of Birmingham
Duration: 3 phases over 10 months

FULL PACKAGE COMPRISED OF:

Key Achievements

Sustainability Efforts

97%

97%
97%

Overall material recovery rate across all waste streams

0 %

of total waste diverted from landfill