Colmore Gate
320,000 sqft site
Project Overview
This comprehensive project involved the full-strip out of a 14 floor office building located in the heart of Birmingham City Centre.
Phase 1 consisted of derating certain floors the building.
Phase 2 consisted of a soft strip of 10 floors whilst maintaining the use of floors 11-14 with live tenants.
Phase 3 consisted of a full soft strip.
Location: Centre of Birmingham
Duration: 3 phases over 10 months
FULL PACKAGE COMPRISED OF:
- Carried out pre-strip out surveys
- Risk assessments and site setup
- Pavement closures and hoarding licenses
- Full strip out
- Waste sorting and recycling
- Coordination with Local Authority
Key Achievements
- Maintained strict 3 phase programme
- Liaised with local businesses and ensured minimal disruption to local tenants
- Implemented dust control on a live site
Sustainability Efforts
97%
97%
97%
Overall material recovery rate across all waste streams
0
%
of total waste diverted from landfill